Gambrel shed

10x12 ft

Gambrel shed plans in ten sizes, with a storage loft, T1-11 siding, double doors and illustrated assembly instructions.

  • Revision: 6
  • Last updated:
  • Steps: 63
  • Difficulty: advanced
  • License: Copyright 2026 DIYplans.org. All rights reserved.
Before you start
  • Unverified concept materials. Not construction-ready. Obtain independent qualified design and review before building.
  • Obtain the foundation, anchorage, wind and snow design, wall bracing, roof-spread restraint, door header and connection details before construction. Revise drawings and schedules if those details change the dimensions.
  • Have the two-ply 2×8 loft beam checked for the selected species, grade, ply fastening, bearing and joist connections. Establish the light-storage load limit, occasional access and edge protection before using the loft.
  • Use engineered roof-joint connections. The 42 plates shown are placement guides; nonstructural mending plates are unsuitable. Select the connectors and installation process before assembly.
  • Choose the T&G floor panels, T1-11 siding, roofing and door hardware before buying dependent materials. Follow their instructions for gaps, laps, clearances, fastening and weatherproofing.
  • The floor layout needs a full 48-inch panel face with the scheduled factory tongues and grooves. Check profile engagement and perimeter gaps before cutting.
  • Use 16 sheets of 5/8-inch T1-11 for the walls, gables and door skins, with grooves vertical. Check delivered thickness and usable lap coverage; adjust trim and door-face offsets if a 19/32-category panel differs.
  • Resolve door sag resistance, rated hinge attachments, fixed-leaf retention and other hardware details before building the doors.
  • Choose roof ventilation, insulation, vapor control and lining attachments before closing cavities. Electrical work is not specified.
  • Use the 10×12 drawings and cut lists together. Keep continuous members whole, label parts and reserve allocated offcuts.
  • Measure delivered board lengths before cutting. Full-length 8, 10 and 12-foot pieces have no end-trimming reserve. Buy the listed stock lengths rather than substituting precut studs. Obtain longer stock when the ends need trimming.
  • Store lumber and panels flat, dry and off the ground. Support sheets during cutting and protect their factory edges.
  • Plan wall and roof lifts, temporary bracing, work platforms and fall protection before assembly.
Plan details

10x12 ft

A 120-square-foot shed with evenly spaced continuous skids, a five-sheet T&G floor, a wall-supported rear loft, paired gambrel end frames, layered roofing, T1-11 plywood siding throughout and exterior-framed double doors.

Choose your shed size to find matching drawings, materials, cut lists, editable CAD and assembly animations. Each complete package includes three printable PDFs. These are unverified design concepts; arrange qualified review of site loads, foundations and structural connections before building.

Open the matching FreeCAD model or import the STEP model. All dimensions are based on actual dressed material sizes.

Use the plan datum: X left to right, Y front to rear and Z upward. Main floor top is Z=0. Read the shaped-profile coordinates before cutting roof members.

Keep CAD, material schedules and instructions at revision 5 together. Apply the completed connection and product selections before construction.

Dimensions and opening sizes
Floor widthAcross the door wall, outside framing.
120 in
Floor depthFront to back, outside framing.
144 in
Floor area
120 ft²
Wall height
84 in
Door opening width
64 in
Door opening height
72 in
Loft depth
48 in
Loft deck height
80 3/4 in
Shopping & cut lists

Get the shopping and cut lists

Includes all available CAD files, shopping lists and cut lists for every configuration of this plan. One payment, $19 USD plus applicable tax.

Get the plan package · $19
Tools & equipment
  • Tape measure long enough for the floor diagonals; pencil and chalk line
  • Framing square, speed square and straightedge
  • Level, string line, and a laser or water level
  • Circular saw and supported sheet-cutting surface
  • Miter saw or clamped guide for repeat cuts
  • Jigsaw or suitable saw for shaped panel and spacer cuts
  • Drill-driver, pilot bits and bits matched to the specified fasteners
  • Hammer or nailer compatible with the specified nails
  • Clamps, sawhorses and a flat wall and roof-frame assembly platform
  • Foundation tools appropriate to the selected site design
  • Utility knife, roofing blade and tin snips
  • Caulk gun, brushes and rollers
  • Stable ladders, work platforms and planned lifting and roof-access equipment
  • Eye, hearing and dust protection; work gloves

BEFORE YOU BUILD

Use this work at your own risk

These files have not been checked for accuracy, safety, structural adequacy, or building-code compliance. They may contain serious errors and are not construction-ready. Obtain independent qualified design and review before building.

No person or organization makes any guarantee or warranty, express or implied, regarding this design, its documentation, digital files, or website views. They are not professional services and do not create an architect-client or other professional-client relationship. No promise is made about accuracy, completeness, reliability, code compliance, or fitness for your project.

Buildings and building projects are complex, and many things can go wrong. You are responsible for checking dimensions and site conditions, choosing suitable materials and methods, obtaining permits, following codes and manufacturer instructions, and getting qualified professional help when needed. To the fullest extent permitted by law, DIYPlans.org disclaims liability for damages resulting from use of this work. Read the FAQ about your responsibilities.

Instructions

Download

Step 1 Confirm the construction details

  • Use the 10×12 drawings and cut lists. Confirm the 120 × 144-inch floor, 84-inch wall height and 64 × 72-inch door opening.
  • Keep the construction details, fastening schedules and selected product instructions beside this guide.
  • Resolve the loft load limit and access details before use.

Check: The site-specific drawings and selected product instructions are available beside this guide.

Step 2 Lay out the footprint

  • Mark a 120 by 144-inch rectangle for the outside of the floor framing. Label the door end as front.
  • Use the front-left outside floor corner as the datum. Measure X across the door wall, Y toward the rear and Z upward from the finished floor.
  • Compare both diagonals and adjust the rectangle until they match. Keep the corners marked while placing the foundation.
  • Mark skid centerlines at 5 1/4, 41 3/4, 78 1/4 and 114 3/4 inches from the left floor edge.

Check: All three skid center spacings are 36 1/2 inches; the floor footprint is square.

Step 3 Prepare the foundation

  • Build the site-specific bearing pads or foundation on suitable ground using its specified drainage, depth and support spacing.
  • Set all skid bearing points to the same elevation. Check the full 12-foot length of each support line with a level or string.
  • Install the specified anchorage provisions while they remain accessible. Keep wood clear of soil and preserve the selected ground clearance.
Reference drawings:

Check: The four support lines are stable, level and ready for continuous skids.

Step 4 Cut and mark the floor members

  • Keep each of the four treated 4x4 skids and both treated 2x6 side rims as one continuous 144-inch board.
  • Cut ten treated 2x6 joists to 117 inches and eight treated 2x6 bearing blocks to 5 1/2 inches.
  • Lay the two side rims side by side and mark joist centerlines at 3/4, 16, 32, 48, 64, 80, 96, 112, 128 and 143 1/4 inches from the front end.
  • Mark each board with its cut-list part number and crown direction. Treat cut ends as required by the preservative supplier.
Reference drawings:

Check: Matching marks on both bare rims locate every joist before assembly.

Step 5 Set the four skids

Play animationStop animationSet the four skids. Current components highlighted in orange against the previously installed gray framing. Movement.
Set the four skids. Current components highlighted in orange against the previously installed gray framing.
  • Place the four continuous 12-foot treated 4x4s on the prepared supports, running front to rear.
  • Align their front ends with the front floor datum and their centers with the four marked lines.
  • Check 36 1/2 inches between neighboring centers, or 33 inches clear between neighboring skid faces.
  • Secure the skids using the foundation anchorage detail and recheck level along and across all four.
Reference drawings:

Check: The outer skid faces lie at 3 1/2 and 116 1/2 inches from the left floor edge.

Step 6 Assemble the floor perimeter

  • Position the two 144-inch side rims along the outside floor edges.
  • Fit a 117-inch joist between them at each end, with its outside face flush with the ends of the rims.
  • Hold the rim and joist top edges in one plane and connect the corners using the framing schedule.
Reference drawings:

Check: The outside frame measures 120 by 144 inches.

Step 7 Install the interior floor joists

  • Fit the eight remaining 117-inch joists between the side rims at the marked 16 through 128-inch centerlines.
  • Set each crown up and bring its top edge flush with the perimeter framing.
  • Seat every joist on all four skids and connect its ends with the specified fasteners or connectors.
Reference drawings:

Check: All ten joists bear on four skids, giving 40 joist-to-skid contacts.

Step 8 Install the loft bearing blocks

  • Fit four of the 5 1/2-inch blocks beside each side rim at the loft-support location shown in the floor drawing.
  • Keep their tops flush with the joists and their bottoms seated on the outer skids.
  • Use the specified connections to transfer the wall-support load through these blocks.
  • Fit all eight blocks. Add support beneath floor seams only if the selected T&G product requires it.

Check: Both wall-supported beam ends have their four floor bearing blocks in place.

Step 9 Square and anchor the floor

  • Compare the floor diagonals, adjust the frame square and recheck level.
  • Complete the specified floor-to-skid and skid-to-foundation connections before covering them.
  • Check each joist and bearing-block contact for a gap, then correct the support or fit using the foundation detail.
  • Confirm the selected 23/32-inch floor panels will finish at the intended floor datum.
Reference drawings:

Check: The frame is square, level, connected and ready for decking.

Step 10 Plan the five T&G sheets

  • Use five 23/32-inch T&G sheets with the full 48-inch face width required by this layout. Check the actual product face width, profile engagement and thickness before cutting.
  • Follow the six-panel layout and factory-edge schedule. Crosscut two 48 by 47 7/8-inch panels from one sheet; use two whole-width sheets for the 95 7/8-inch panels.
  • Rip each of the two 23 3/4-inch-wide right-edge panels from a separate sheet, measuring from the factory groove. Keep both groove edges intact.
  • Run the panel strength direction front to rear, across the floor joists. Dry-fit profile engagement and required gaps; revise the layout if the selected product requires different dimensions.
Reference drawings:

Check: Six panels come from five sheets, with the correct factory tongue or groove at every unsupported long-edge joint.

Step 11 Lay the left floor strip

  • Place the 48 by 95 7/8-inch panel in the front-left position, with its factory tongue facing right.
  • Place the 48 by 47 7/8-inch panel behind it. Center their cross joint over the joist at 96 inches from the front.
  • Maintain the selected product gaps. The drawn cross joint is 1/8 inch and the drawn front and rear body setbacks are 1/16 inch.
  • Fasten the panels to the joists using the panel schedule, applying subfloor adhesive only if required by the selected system.
Reference drawings:

Check: The left strip is straight and its factory tongues remain available for the middle strip.

Step 12 Lay the middle floor strip

  • Place the 48 by 47 7/8-inch panel at the front and the 48 by 95 7/8-inch panel behind it.
  • Engage the left grooves with the first strip without damaging or forcing the profiles.
  • Center this strip’s cross joint over the 48-inch joist, staggering it from the left strip’s joint.
  • Maintain the required gaps and fasten the panels with their right factory tongues exposed.
Reference drawings:

Check: The middle strip is joined to the first strip and its cross joint is supported.

Step 13 Finish the right floor strip

  • Engage the two 23 3/4-inch-wide panels with the middle strip, keeping their intact factory grooves toward the left.
  • Place the 95 7/8-inch panel at the front and the 47 7/8-inch panel behind it, with the cross joint over the 96-inch joist.
  • Trim only the outside perimeter edge if the selected product and field measurement require it.
  • Complete the floor fastening and check for high edges, missed joists and damaged T&G profiles before framing the walls.
Reference drawings:

Check: The six fitted floor pieces cover the 120 by 144-inch frame.

Step 14 Cut and mark the wall stock

  • Keep the side-wall bottom and first top plates as continuous 144-inch boards. Cut the side cap plates to 137 inches and keep them aside.
  • Cut the regular and corner-backing studs to 79 1/2 inches. Mark each bare plate from the front floor datum using the wall layout.
  • At each side-wall loft seat, mark the front king stud at Y 91 to 92 1/2 inches, two jack studs at Y 92 1/2 to 95 1/2 inches, and the adjacent regular stud at Y 95 1/2 to 97 inches.
  • Cut the four loft jack studs to 71 1/4 inches. Keep the rear and front wall members labeled separately from the side-wall stock.

Check: The wall layout includes corner backing and the two beam seats before assembly.

Step 15 Assemble and raise the left wall

Play animationStop animationAssemble and raise the left wall. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and raise the left wall. Current components highlighted in orange against the previously installed gray framing.
  • Build the left wall flat on a clear platform using its bottom plate, first top plate and twelve full-height studs, including the corner backing.
  • Install the extra full-height king stud and the two 71 1/4-inch jack studs at the loft seat. Keep the beam pocket open above the jacks.
  • Square the frame and fasten it using the wall schedule. Leave the second top plate off.
  • Use enough helpers and the planned lifting method to raise the wall onto the left floor edge. Plumb, secure and temporarily brace it before releasing it.

Check: The wall is plumb and braced, and its loft jacks end 72 3/4 inches above the floor.

Step 16 Assemble and raise the right wall

Play animationStop animationAssemble and raise the right wall. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and raise the right wall. Current components highlighted in orange against the previously installed gray framing.
  • Build the matching right wall with its continuous plates, twelve full-height studs, corner backing and three additional loft-seat members.
  • Measure the loft jack positions from the same front datum used for the left wall.
  • Square and connect the frame, then raise it onto the right floor edge with helpers.
  • Plumb, secure and brace the wall. Check that the two beam seats face one another at the same height.

Check: Both side walls are braced, parallel and ready to receive the end walls.

Step 17 Assemble and raise the rear wall

Play animationStop animationAssemble and raise the rear wall. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and raise the rear wall. Current components highlighted in orange against the previously installed gray framing.
  • Build the rear wall with 113-inch bottom and first top plates and nine 79 1/2-inch studs.
  • Use the rear-wall drawing for stud marks; measure X from the left floor edge when checking its installed position.
  • Raise the wall between the two side walls, flush with the rear floor edge.
  • Plumb and connect the corners, then brace the wall. Keep the 120-inch cap plate aside.
Reference drawings:

Check: The rear wall fits between the side walls without forcing their alignment.

Step 18 Lay out the door wall

  • Mark the 64-inch opening from X 28 to X 92 inches on the bare front-wall layout.
  • Cut two 24 1/2-inch bottom-plate pieces, one 113-inch first top plate and the scheduled full-height, jack and cripple studs.
  • Prepare two 67-inch 2x6 header plies and the 67 by 5 1/2-inch, 1/2-inch plywood spacer, subject to the reviewed header design.
  • Keep the opening clear from the finished floor to the header underside at 72 inches. Do not carry a permanent bottom plate across the doorway.
Reference drawings:

Check: The labeled parts preserve a 64 by 72-inch rough opening.

Step 19 Assemble and raise the front wall

Play animationStop animationAssemble and raise the front wall. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and raise the front wall. Current components highlighted in orange against the previously installed gray framing.
  • Build the front frame flat, with full-height king studs beside the opening and the 70 1/2-inch jack studs below the header.
  • Assemble the reviewed two-ply header with its 1/2-inch spacer. Seat it on both jacks and install the six short cripples above it.
  • Square the frame while checking the 64 by 72-inch opening. Use temporary handling bracing as needed to hold the two bottom-plate sections in position.
  • Raise the wall with helpers, connect it between the side walls and brace it plumb. Keep the doorway clear and leave the cap plate off until the corners are checked.
Reference drawings:

Check: The header has its specified bearing and the door opening remains square.

Step 20 Tie the wall tops together

  • Recheck wall plumb, corner connections and the two floor diagonals before adding the cap plates.
  • Fit the two 137-inch side cap plates between the end-wall caps.
  • Fit the 120-inch front and rear cap plates across the full shed width, lapping over the side-wall plates at the corners.
  • Connect the laps and plates using the wall schedule. Keep temporary bracing until the specified permanent bracing replaces it.
Reference drawings:

Check: All wall tops finish at 84 inches and the cap-plate laps tie the four walls together.

Step 21 Lay out the loft

  • Confirm the reviewed beam species, grade, two-ply fastening and wall-seat connections before cutting the loft stock.
  • Use two continuous 120-inch 2x8 beam plies, a 113-inch 2x6 rear ledger and nine 2x6 joists.
  • Treat the 44 7/8-inch joist length as dependent on the selected front hanger. The model leaves a 1/8-inch gap to the beam and retains 1 1/2-inch rear ledger bearing.
  • Mark joist centers at X 4 1/4, 16, 32, 48, 64, 80, 96, 112 and 115 3/4 inches. Plan access and edge protection before the loft is used.
Reference drawings:

Check: The connector selection agrees with the beam, joist lengths and wall bearing details.

Step 22 Set the two-ply loft beam

Play animationStop animationSet the two-ply loft beam. Current components highlighted in orange against the previously installed gray framing. Movement.
Set the two-ply loft beam. Current components highlighted in orange against the previously installed gray framing.
  • Join the two continuous 2x8 plies using the reviewed load-sharing and fastening detail.
  • Keep the side-wall pockets open and provide clear access outside the left wall. With helpers and suitable temporary supports, feed the beam horizontally through the left pocket toward the right seat.
  • Slide the beam into position until each end bears across the full 3 1/2-inch wall width on its two jack studs. Keep its front face at Y 92 1/2 inches and rear face at Y 95 1/2 inches.
  • Secure the beam and verify its top at 80 inches above the floor. Leave the area beneath the loft clear of vertical posts.

Check: The beam bears on both wall seats and its underside is 72 3/4 inches above the floor.

Step 23 Attach the rear loft ledger

  • Position the 113-inch 2x6 ledger against the inside rear-wall studs, between the side walls.
  • Set its top at 74 1/2 inches above the finished floor and check it level.
  • Attach it to the wall studs using the reviewed structural connection schedule. Do not substitute a generic screw pattern.
  • Check the rear wall and ledger connections before placing joists.

Check: The ledger provides the planned 1 1/2-inch bearing beneath the rear joist ends.

Step 24 Install the loft joists

  • Fit the selected joist hangers or reviewed connections to the rear face of the loft beam at the marked centers.
  • Set the nine joists crown up, with their front ends seated in the connectors and their rear ends bearing on the ledger.
  • Install every required connector fastener and any specified restraint or panel-edge support before covering the framing.
  • Check that the joist tops align with the beam top at 80 inches. Keep the loft unloaded.

Check: Each joist has a completed front connection and full rear bearing; no joist is left supported by end nails alone.

Step 25 Lay the loft deck

  • Cut the two 3/4-inch panels to the sheet layout, keeping their strength direction across the shed width and perpendicular to the joists.
  • Fit the larger panel at the left and the smaller panel at the right, with the 1/8-inch drawn cross joint over the joist at X 96 inches.
  • Check all perimeter and joint support, then fasten using the selected panel schedule.
  • Keep the loft unused until its connections, permitted load, access and required edge protection are complete. Do not treat the deck as a roof-framing work platform without a suitable work plan.
Reference drawings:

Check: The deck measures 113 by 48 inches overall and its finished top is 80 3/4 inches above the floor.

Step 26 Lay out the gambrel cuts

  • Mark a full-size gambrel profile or make a stable assembly jig from the exact profile drawings.
  • Start the lower rafters from 39 7/8-inch rough blanks and the upper rafters from 45 11/16-inch rough blanks. These allowances exceed the finished profile lengths; do not use the blank length as a finished long-point dimension.
  • Cut one matched set of four rafters and check the joints against the full-size profile before repeating it.
  • Prepare 28 rafters for seven outer stations and eight additional rafters for the inner front and rear frames. Cut the eight 1/2-inch spacer profiles with their joint-plate reliefs.

Check: The four-rafter template spans 120 inches and matches the exact knee and ridge profiles.

Step 27 Prepare the roof connections

  • Obtain the designed knee and ridge connections, wall ties, spread restraint and erection bracing before assembling or lifting a frame.
  • Use the specified structural connectors and installation method. Pressed tooth plates require their specified manufacturing process.
  • For the two paired end frames, resolve the connections inside the 1/2-inch cavity before closing the pair. Keep the outer siding face and inner lining face unobstructed.

Check: The roof connection details cover every joint, both paired end frames and the required restraint.

Step 28 Assemble and set the front roof frame

Play animationStop animationAssemble and set the front roof frame. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and set the front roof frame. Current components highlighted in orange against the previously installed gray framing.
  • Assemble the four outer rafters on the checked jig using the designed joints.
  • Complete the cavity-side joint connections, fit the four relieved 1/2-inch plywood spacers and add the matching inner four-rafter frame in the designed assembly order.
  • Check the paired frame’s total thickness of 3 1/2 inches and its clear outside and inside faces.
  • Lift the complete assembly with the planned equipment and helpers. Set its outside face at the front wall line, plumb it and secure the designed temporary and permanent restraints before release.

Check: The front pair occupies Y 0 through 3 1/2 inches, with its inside face flush with the future gable infill.

Step 29 Set the first interior roof frame

Play animationStop animationSet the first interior roof frame. Current components highlighted in orange against the previously installed gray framing. Movement.
Set the first interior roof frame. Current components highlighted in orange against the previously installed gray framing.
  • Assemble another four-rafter frame on the jig, completing the designed joints on both faces.
  • Mark its centerline 24 inches from the front floor edge on both wall caps.
  • Lift the frame into place, check its bearing and plumb it against the front frame.
  • Fit the specified wall ties, temporary spacing and diagonal bracing before releasing the frame.
Reference drawings:

Check: The first interior frame is secured at the 24-inch centerline without relying on loose spacers for bracing.

Step 30 Set the remaining interior roof frames

  • Assemble the four remaining interior frames to the same checked jig and connection detail.
  • Set their centers at 48, 72, 96 and 120 inches from the front floor edge.
  • Lift and brace one complete frame at a time. Keep the knees, ridge and wall bearing lines aligned.
  • Complete the specified ties and erection bracing as each frame is placed.
Reference drawings:

Check: All five interior frames are aligned at their scheduled centers and remain braced.

Step 31 Assemble and set the rear roof frame

Play animationStop animationAssemble and set the rear roof frame. Current components highlighted in orange against the previously installed gray framing. Movement.
Assemble and set the rear roof frame. Current components highlighted in orange against the previously installed gray framing.
  • Build the rear paired frame with its outer four rafters, cavity joint connections, relieved spacers and inner four rafters.
  • Check the full 3 1/2-inch thickness before lifting it.
  • Set its rear outside face flush with the rear wall line at Y 144 inches. Its inner face belongs at Y 140 1/2 inches.
  • Plumb, tie and brace the frame, then check the complete roof for straight ridge and knee lines.
Reference drawings:

Check: Both end pairs and all five interior frames are secured before gable infill or roof panels are added.

Step 32 Cut the gable infill

  • Mark the seven front and seven rear 2x4 infill studs using the individual cut profiles.
  • Start with the scheduled rough blank lengths and cut each top to the exact roof-underside shape.
  • Keep the 3 1/2-inch stud depth running front to rear, perpendicular to the flat rafter faces.
  • Label each position from left to right. The off-center stud layout gives different heights on the two sides; do not substitute mirrored cuts.

Check: Fourteen labeled studs fit their individual positions between the wall caps and roof profile.

Step 33 Install the front gable infill

  • Set the seven front infill studs on the front cap plate at X 16, 32, 48, 64, 80, 96 and 112-inch centers.
  • Keep their full 3 1/2-inch depth between Y 0 and 3 1/2 inches.
  • Fit their profiled tops under the paired roof members and attach them using the gable framing detail.
  • Check the inner faces against the added inner rafters. Keep the future lining plane clear.
Reference drawings:

Check: The infill remains perpendicular and its inside face aligns with the inner end frame.

Step 34 Install the rear gable infill

  • Set the seven rear studs at the same X centerlines, using their labeled profiles.
  • Keep their depth between Y 140 1/2 and 144 inches and their bottoms on the rear cap plate.
  • Connect the infill and check its inside face flush with the rear inner rafters.
  • Resolve roof ventilation, insulation depth, vapor control and lining attachment before adding any interior insulation or lining; those layers are not specified here.
Reference drawings:

Check: The rear end has the same continuous inside framing plane as the front end.

Step 35 Prepare the wall weather details

  • Use 5/8-inch T1-11 exterior plywood siding for every wall, gable and door skin. Keep the face grooves vertical and confirm the panel rating, usable coverage and required edge joints.
  • Install the specified weather barrier and door sill, jamb and head flashings in their product sequence before covering their attachment areas.
  • Plan flashing at the horizontal gable-to-wall joint. The later 1x4 seam trim conceals the joint but does not replace its weather detail.
  • Keep the designed wall bracing in place and verify panel-edge support before fastening the siding.
Reference drawings:

Check: Each opening and joint has a drainage path to the exterior and the selected panel system has its required backing.

Step 36 Panel the left wall

  • Cut the three 84-inch-high left-wall T1-11 panels to the sheet layout, with vertical face orientation as specified by the panel product.
  • Start at the front and align the two vertical joints with the studs at Y 48 and 96 inches.
  • Keep the required joint gaps, bottom clearance and edge support while the wall remains plumb and braced.
  • Fasten each panel using the wall-panel schedule and protect the cut edges.
Reference drawings:

Check: The left wall panels are fully fastened with supported joints and the specified clearances.

Step 37 Panel the right wall

  • Fit the three right-wall T1-11 panels in front-to-rear order, using the matching sheet widths.
  • Align the joints at Y 48 and 96 inches and check the selected panel gaps before fastening.
  • Keep the wall plumb and preserve the required clearance above grade and adjacent surfaces.
Reference drawings:

Check: The right wall has the same panel support and joint spacing as the left wall.

Step 38 Panel the rear wall

  • Fit the two wider rear T1-11 panels from the left, followed by the narrow right panel.
  • Align the panel joints at X 48 and 96 inches and keep their top edges at the 84-inch wall line.
  • Fasten using the panel schedule without closing the required joints.
Reference drawings:

Check: The rear wall enclosure ends at a straight horizontal gable joint.

Step 39 Panel the door wall

  • Transfer the installed 64 by 72-inch door opening to the three front panels using the shaped-panel drawings.
  • Support each blank before cutting the opening portions. Check the cutout against the actual header and jamb locations.
  • Fit and fasten the panels around the opening, keeping product clearances and the door flashing intact.
  • Keep the full door opening clear before measuring for the leaves.

Check: The opening remains square and unobstructed, with solid backing at the panel edges.

Step 40 Mark the gable panels

  • Lay out the six 5/8-inch T1-11 gable-panel blanks on the scheduled sheets, preserving the specified face orientation.
  • Transfer each exact top profile from its drawing, then check it against the installed roof before cutting.
  • Label the three front and three rear pieces separately and seal the cut edges as required.
  • Preserve the vertical panel-joint gaps and the selected weather detail at the horizontal wall joint.
Reference drawings:

Check: Each shaped gable panel matches its own position; the narrow and wide profiles are not interchangeable.

Step 41 Panel the front gable

  • Fit the three front gable panels from left to right above the 84-inch wall line.
  • Check their joints over the gable framing and their roof-edge clearances before fastening.
  • Complete the specified horizontal-joint flashing while access remains open.
Reference drawings:

Check: The front gable panels follow the roof profile and their horizontal joint is ready for seam trim.

Step 42 Panel the rear gable

  • Fit the three rear gable panels to their labeled positions and check the profile against the roof.
  • Keep the required joint gaps and fasten to the intended framing.
  • Complete the rear horizontal-joint weather detail and the specified permanent wall bracing before removing any temporary brace it replaces.
Reference drawings:

Check: Both gables are enclosed and the permanent wall system is connected.

Step 43 Cut the roof-deck panels

  • Prepare eight 1/2-inch roof panels from the sheet layout, keeping their strength direction front to rear across the roof frames.
  • Use rough slope-width blanks of 39 7/8 inches for the four lower-facet panels and 45 11/16 inches for the four upper-facet panels. Finish each to its exact cut profile.
  • Cut the front-to-rear panel length to 75 15/16 inches. Each facet has two panels with a 1/8-inch drawn joint over the frame at Y 72 inches.
  • Confirm the selected panel span rating, edge support, fastening and 4-inch gable overhang detail before installation.
Reference drawings:

Check: The eight panels are labeled by facet and front or rear position, with strength arrows retained.

Step 44 Sheath the lower roof facets

  • Use the planned work platforms and roof access. Recheck roof bracing before placing panels.
  • Fit the front and rear panels on the left lower facet, with 4-inch projections beyond both gable framing faces.
  • Fit the matching two panels on the right lower facet. Maintain the selected edge gaps and support details.
  • Fasten to the roof frames using the panel schedule while keeping the knee lines straight.
Reference drawings:

Check: The four lower panels have supported joints and consistent gable projections.

Step 45 Sheath the upper roof facets

  • Fit the two upper-left panels and the two upper-right panels using the matching strength directions and gable projections.
  • Maintain the required panel gaps at the middle station, knees and ridge.
  • Install specified panel-edge support and fasten every supporting frame.
  • Complete any concealed permanent roof restraint and connection work before access is lost.
Reference drawings:

Check: All four facets match the knee and ridge profiles without forced joints.

Step 46 Check the roof deck

  • Inspect panel joints, edge support, frame alignment and the gable projections from safe access.
  • Correct missed framing, overdriven fasteners and any loose or unsupported panel corners.
  • Confirm that the selected roofing system accepts both roof pitches and includes a suitable gambrel knee transition.
  • Resolve any required membranes and ventilation openings before applying the weather layers.
Reference drawings:

Check: The roof deck and concealed connections are complete and ready for the selected roof system.

Step 47 Fit the eave drip edges

  • Use the roofing manufacturer's instructions for laps, fasteners, exposure and edge details throughout the roofing steps.
  • Fit drip edge along the two long eaves before the underlayment where required by the selected roof system.
  • Choose an eave profile whose vertical return clears the 5/8-inch T1-11 face while its upper flange remains seated on the roof deck. Keep its lower edge free to drain.
  • Resolve the four eave and corner-trim terminations before fastening the metal. Follow the selected flashing detail and preserve clearance for the 84-inch corner boards installed in step 60.
  • Cover the 152-inch roof length with each run. Allow for the specified laps and end details when cutting stock.
Reference drawings:

Check: Both eaves have continuous outward-draining edge metal.

Step 48 Apply the roof underlayment

  • Install any required eave membrane, then apply underlayment across all four facets using the selected system’s order.
  • Work from low to high with upper courses shedding onto lower courses. Use the required laps and temporary or permanent fasteners.
  • Complete the specified knee and ridge weather-layer details and preserve designed ventilation openings.
Reference drawings:

Check: Every facet and both pitch changes have the required continuous weather protection.

Step 49 Fit the rake drip edges

  • Install edge metal along the four slopes at each gable, following the roofing system’s order relative to the underlayment.
  • Miter or form the knee and ridge junctions using the selected metal detail.
  • Lap successive stock pieces and terminate them at the eaves as specified so water drains onto the eave edge.
Reference drawings:

Check: Both gable roof edges have continuous metal with finished knee and ridge junctions.

Step 50 Shingle the lower roof facets

  • Install the selected starter course along each eave using the product’s edge and rake details.
  • Lay the lower-facet field shingles from eave toward knee, following the specified exposure, stagger and nail pattern.
  • Check the drawn eight courses and 5-inch exposure against the selected shingle product; adjust the course layout if needed.
  • Finish the last lower course in the position required to receive the knee-flashing apron.
Reference drawings:

Check: Both lower facets are shingled and ready for the transition flashing.

Step 51 Flash the gambrel knees

  • Fit the selected transition flashing along each change in roof pitch.
  • Place its lower apron above the completed lower shingles and its upper flange where the upper shingles will cover it.
  • Form the correct bend for the actual roof pitches and complete the prescribed side laps and rake terminations.
  • Follow the flashing detail for fastening and its connection to the membrane.
Reference drawings:

Check: Each knee sheds from the upper roof over the flashing and onto the lower shingles.

Step 52 Shingle the upper roof facets

  • Start the upper courses at each knee using the selected transition detail, covering the flashing’s upper flange.
  • Work toward the ridge with the required exposure, joint offset and fasteners.
  • Check the drawn ten courses against the selected roofing product and adjust the layout if needed.
  • Preserve the designed ridge closure or vent space and finish the rake edges as specified.
Reference drawings:

Check: Both upper facets shed onto the knee flashings without leaving an exposed upper flange.

Step 53 Finish the ridge

  • Install the selected ridge closure and any designed ridge ventilation before the caps.
  • Lay the ridge-cap units with the specified exposure, laps, fasteners and final closure detail.
  • Inspect all eaves, rakes, knees and ridge terminations before removing roof access equipment.
Reference drawings:

Check: The selected roof system is complete, including its starter, laps, flashings and ridge details.

Step 54 Cut and lay out the doors

  • Measure the finished opening before cutting the two door leaves to 31 11/16 × 71 5/8 in.
  • Cut two 5/8-inch T1-11 skins from separate sheets with their face grooves vertical. Seal all cut edges as required.
  • For each leaf, cut two full-height 71 5/8-inch exterior 2x4 stiles and three 24 11/16-inch rails that fit between them.
  • Resolve the door fastening, skin bracing and sag resistance with the selected hinges before assembling the leaves. This layout has no diagonal braces.
Reference drawings:

Check: The labeled leaf parts and selected hardware preserve the planned opening clearances.

Step 55 Fit the door jambs and head

  • Fit the two 72-inch exterior 2x4 jamb pieces along the opening sides and the 71-inch 2x4 head above them.
  • Keep the outer faces aligned with the future exterior door-frame faces.
  • Fasten into the specified solid backing and integrate the head flashing over the opening trim.
  • Recheck a clear 64 by 72-inch opening and mark the selected hinge positions.
Reference drawings:

Check: The jambs are plumb, the head is level and the hinge backing is ready.

Step 56 Build and hang the left door

Play animationStop animationBuild and hang the left door. Current components highlighted in orange against the previously installed gray framing. Movement.
Build and hang the left door. Current components highlighted in orange against the previously installed gray framing.
  • Lay the left skin on a flat supported surface. Fit the two full-height stiles and three rails on its exterior face, using the door drawing for rail positions.
  • Clamp the assembly square and fasten the skin and framing with the resolved door connection detail.
  • Fit the selected hinges and support the completed leaf on blocks while attaching it to the jamb backing.
  • Set a 1/8-inch hinge-side gap, 1/8-inch top gap and 1/4-inch bottom gap. Check the hinge travel before removing the supports.
Reference drawings:

Check: The left leaf is supported by its selected hinges and holds its clearances without sagging.

Step 57 Build and hang the right door

Play animationStop animationBuild and hang the right door. Current components highlighted in orange against the previously installed gray framing. Movement.
Build and hang the right door. Current components highlighted in orange against the previously installed gray framing.
  • Assemble the right leaf with its skin, two exterior stiles and three rails, keeping the completed leaf square.
  • Attach the selected hinges, support the leaf and fasten it to the right jamb backing.
  • Set the same 1/8-inch side and top gaps and 1/4-inch bottom gap, with 3/8 inch between the closed leaves.
  • Swing each leaf through its intended travel and correct rubbing or sag before fitting the meeting strip.
Reference drawings:

Check: Both leaves swing and close with an even 3/8-inch meeting gap.

Step 58 Fit the meeting strip

  • Close and align both leaves, then fit the 71 5/8-inch 1x2 meeting strip over the center gap.
  • Attach it to the designated active leaf only, using the selected door arrangement and fasteners.
  • Keep its position compatible with the leaf-opening order, latch and any selected weather seals.
  • Recheck both leaves through their intended travel without forcing the strip against the opposite frame.
Reference drawings:

Check: The strip covers the meeting gap and the doors operate in the intended order.

Step 59 Install the door hardware

  • Install the selected pull and latch into their required solid backing.
  • Fit the fixed-leaf bolts, receivers, stops and weather seals required by the selected hardware detail.
  • Operate the latch and any bolts with the doors open and closed, then verify that both leaves reopen freely.
  • Check the hardware manufacturer’s required fasteners and edge distances.
Reference drawings:

Check: The doors close, secure and reopen without binding or pulling the leaves out of square.

Step 60 Fit the corner trim

  • Measure the finished siding and cut eight 84-inch 1x4 corner boards to fit.
  • Fit each front or rear corner board over the 3/4-inch edge of its side return. Seat both boards against the T1-11 faces; use the corner detail to close the return without a gap.
  • Keep the required bottom clearance and seal or prime cut ends before fastening.
  • Fasten into the intended backing without closing required siding joints or drainage paths.
Reference drawings:

Check: All four wall corners are covered with supported trim and finished cut ends.

Step 61 Cover the gable-to-wall seams

  • Cut one continuous 115 3/4-inch 1x4 from each of two 10-foot boards.
  • Fit one board across the front and one across the rear between the existing corner trims.
  • Center each board on the panel joint 84 in above the floor, with its lower edge at 82 1/4 in and upper edge at 85 3/4 in.
  • Preserve the selected joint flashing and drainage detail behind the trim, then fasten into the specified backing and finish the cut ends.

Check: Two continuous boards conceal the front and rear horizontal panel joints without replacing their flashing.

Step 62 Seal and finish the exterior

  • Allow the wood and panels to dry to the coating manufacturer’s limits.
  • Seal only the joints required by the selected siding, trim and door products. Keep drainage and ventilation openings clear.
  • Prime exposed cut edges and unfinished surfaces, then apply the specified exterior finish coats.
  • Protect roofing and door hardware from paint and recheck the door clearances after finishing.

Check: The exterior has its required finish and all intended drainage paths remain open.

Step 63 Inspect before use

  • Compare the foundation-to-roof connections, panel fastening and permanent bracing with the completed construction details.
  • Check wall plumb, roof alignment, flashing terminations, trim support and the operation of both doors.
  • Remove temporary bracing only where the completed permanent structure replaces it, then clear loose fasteners and offcuts.
  • Record the loft’s permitted use and load limit. Complete its required access, edge protection and inspections before storing anything on it.
  • Keep the final drawings, selected product instructions and connection schedules with the shed records.

Check: The required inspections and remaining product or connection decisions are complete before the shed or loft is used.

Report a problem